Bond Overview
In 2021, voters approved a bond to improve school buildings, facilities and grounds. This Bond Overview section explains the projects that have been completed as part of the 2021 bond proposal and a short list of items still left to complete.
The $41.9 million bond proposal included a new school for kindergarten through second grade, moving Little Glad to Smith, improving air conditioning across the district, and removing the Munn building. The specific items addressed by location are outlined below.
Building and Grounds Projects
Little Glads Early Childhood Center/Smith
- Renovated the building for early childhood programs.
- Added classroom cooling equipment and a new rooftop HVAC unit.
- Installed a secure entrance and new classroom windows/entrance assemblies.
- Added lockers, flooring, cabinets, sinks and electrical/fire-alarm improvements.
- Installed toddler and preschool playgrounds.
- Completed additional concrete and site improvements.
- Installed additional playground and perimeter fencing.
- Completed additional exterior painting and finishing work.
- Completed additional electrical, security, and access-control improvements.
- Completed additional playground improvements.
Fowlerville Elementary School
- Built a new K–2 school with classrooms, library, gym, cafeteria/kitchen, specialized learning spaces and offices.
- Installed new furniture, cabinets, lockers and classroom technology.
- Installed heating, cooling, plumbing, electrical and safety/security systems.
- Built playgrounds and improved bus parking, sidewalks, lighting and landscaping.
- Completed additional water-main infrastructure and utility improvements associated with the new elementary school.
Kreeger Elementary School
- Installed a new chiller, air-handling equipment and classroom HVAC components.
- Added associated piping, insulation and electrical connections.
- Replaced ceilings and restored walls affected by installation.
- Built a concrete pad and protective fencing for the chiller.
- Installed additional air-conditioning equipment in areas not included in the original project, including the art and music rooms.
Fowlerville Junior High
- Replaced existing rooftop HVAC equipment with seven new units.
- Upgraded related wiring, duct insulation and roof supports.
- Restored or replaced ceilings and patched affected walls.
Fowlerville High School
- Installed new chillers, pumps, HVAC controls and cooling coils in existing air-handling units.
- Upgraded piping, insulation, transformer and switchgear.
- Built a protective chiller enclosure and equipment pads.
- Restored ceilings and completed related sidewalk, concrete and site improvements.
Fowlerville High School / Future Farmers of America (FFA)
- Completed portions of the FFA pole barn project and associated site improvements using a combination of funding sources, including bond funds.
- Added a concrete patio and sidewalk improvements to support the FFA instructional area and HS cafeteria outdoor area.
Munn Building
- Completed asbestos abatement and utility disconnections.
- Reconnected exterior light poles to power from Smith.
- Began building demolition as designated in the bond.
- Completed demolition of the former school building and received final permit approval on October 29, 2026.
Central Office
- Installed modular office partitions and created additional administrative workspaces.
- Purchased and installed additional office furniture and workstations.
- Renovated the conference room.
- Installed additional electrical outlets, data connections, and conference-room lighting.
- Completed design and procurement work for replacement exterior office windows.
District Water Infrastructure
- Completed additional water-system mapping and engineering across the campus.
Projects Still Underway as of November 1
There are also a few remaining projects:
- Central Office windows: The replacement exterior windows are scheduled for installation over Christmas break.
- High School water main: The permanent disconnection and capping of the second water connection is scheduled for November 6–7.
- Munn water main: The remaining modifications are still being worked through with the Village.
- Water System: Legal work related to the 1992 easements still needs to be completed including adjustments to the locations based on the water-system mapping.
What language was used for the 2021 bond ballot proposal
2021 Bond Proposal Language
Shall Fowlerville Community Schools, Livingston, Ingham and Shiawassee Counties, Michigan, borrow the sum of not to exceed Forty-One Million Nine Hundred Thousand Dollars ($41,900,000) and issue its general obligation unlimited tax bonds therefor, in one or more series, for the purpose of:
erecting, furnishing, and equipping a new elementary school building; acquiring and installing instructional technology and instructional technology equipment for the new elementary school building; remodeling school buildings; and preparing, developing, improving and equipping playgrounds and sites?
The following is for informational purposes only:
The estimated millage that will be levied for the proposed bonds in 2022, under current law, is 0.9 mill ($0.90 on each $1,000 of taxable valuation), for a -0- mill net increase over the prior year’s levy. The maximum number of years the bonds of any series may be outstanding, exclusive of any refunding, is twenty-three (23) years. The estimated simple average annual millage anticipated to be required to retire this bond debt is 2.86 mills ($2.86 on each $1,000 of taxable valuation).
The school district expects to borrow from the State School Bond Qualification and Loan Program to pay debt service on these bonds. The estimated total principal amount of that borrowing is $9,345,128 and the estimated total interest to be paid thereon is $12,498,023. The estimated duration of the millage levy associated with that borrowing is 19 years and the estimated computed millage rate for such levy is 9.55 mills. The estimated computed millage rate may change based on changes in certain circumstances.
The total amount of qualified bonds currently outstanding is $79,075,000. The total amount of qualified loans currently outstanding is approximately $8,430,173.
(Pursuant to State law, expenditure of bond proceeds must be audited and the proceeds cannot be used for repair or maintenance costs, teacher, administrator or employee salaries, or other operating expenses.)